Dump Scow Barge Maintenance

The SUS team was called in to assist with the maintenance of a dump scow barge. Two commercial diving crews worked in 24-hour rotations to complete the project on schedule and with minimal downtime. The scope of work included welding sacrificial anode protection systems to the barge’s hull to protect the vessel from corrosion and ensure its long-term structural integrity.
Project Gallery
Related Projects

Wicomico River Bridge Rehabilitation
SUS was contracted to rehabilitate two bridges in Wicomico County, Maryland. The scope of work includes installing new concrete filled pipe pile dolphins, new vertical timber fender boards, and new wire bands around the existing timber dolphins, as well as performing underwater epoxy crack injection repairs to abutment walls, performing underwater concrete abutment rehabilitation, and rehabilitating the undermined portions of the abutments. The old timber pile dolphins were replaced by five seven-pile dolphin clusters consisting of 24” by ½” by 90’ steel pipe pile with epoxy coated rebar that was then filled with 5000 psi concrete.

Dump Scow Barge Maintenance
The SUS team was called in to assist with the maintenance of a dump scow barge. Two commercial diving crews worked in 24-hour rotations to complete the project on schedule and with minimal downtime. The scope of work included welding sacrificial anode protection systems to the barge’s hull to protect the vessel from corrosion and ensure its long-term structural integrity.

US Coast Guard Pier Repairs
Specialty Underwater Services (SUS) performed substructure repairs beneath Pier Two at the U.S. Coast Guard’s Baltimore Yard. The scope of work included critical rehabilitation of the pier’s substructure to ensure long-term stability and performance. In addition, our Team replaced the pier curb and completed concrete repairs to the existing crane rail, enhancing both structural integrity and operational functionality along the waterfront.

Arlington Memorial Bridge Rehabilitation
SUS successfully completed underwater concrete repairs and dive support for the Arlington Memorial Bridge. Our team managed 1,438 linear feet of crack repair, enhancing the bridge’s structural stability, and conducted 8.5 cubic feet of spall repair to restore deteriorated concrete areas to their original state. The project also included the meticulous cleaning of 25,920 square feet of granite, significantly improving the bridge’s visual appeal. Furthermore, SUS provided invaluable welding and burning support to the general contractor, demonstrating our ability to deliver comprehensive and effective solutions in complex underwater settings.

Lake Lariat
SUS inspected the existing marine structure catwalk, removed it and installed a new structural catwalk.

Anne Arundel County Fire Line Install
SUS installed a new fire line for Anne Arundel County. Our team mobilized to excavate and remove an existing 6-inch fire line, replacing it with a durable 6-inch HDPE fire line tailored for long-term use. In addition to the pipeline work, SUS installed a roadside adaptor, enabling the Anne Arundel County Fire Department to quickly connect to the water supply in emergency situations.

Havre De Grace Wastewater Treatment Plant
SUS mobilized and installed a concrete support pad to hold a prefabricated storage shed. SUS also excavated and installed 2” and 12” HDPE pipes to be used as the air delivery system.

Center Point Marine Terminal
SUS was contracted for the condition survey and pier construction repairs consisting of heavy timber cap beam and crossbracing replacement. Working hand-in-hand with a unique mix of marine construction and diving personnel, SUS completed this project within a few days and allowed the terminal to stay active during the work. The team also completed some localized debris removal near the mooring area for safety.

Robinson Landing
Specialty Underwater Services was contracted to provide Pier Rehabilitation. The work consisted of the removal of the existing Timber Structures, Dolphins and Piles along with the demolition and removal of the existing boathouse, light poles and pier handrails. Once the demolition work was completed concrete repairs were made to the under-deck of pier, the pier deck itself and the concrete curbs. New Concrete curb was installed along with structural steel repairs. A new “D” fender was installed around the pier and the sheet pile wall was extended for the bulkhead and a new concrete cap was poured.
24-Hour Emergency Response Available
Quick Project Mobilization for Any Emergency Situation
For a direct line to our recognized marine construction and diving contracting team: